Raised Floor Living by Southern Pine Council
Home | About Us | Help Desk |  Search:    
Rediscover Raised Floor Living
 

 Building Pro Locator   
 Top 10 Benefits         
 Key Elements              
 The Advantages        
 Wood Products         
 Construction Process
 Span Tables            
 Construction Details
 Construction Images 
 Special Topics          
 Case Studies           
 Green Building           
 Resources                   

Raised Floor Builder Signup





  Affordable Alternative


The 2,744 sq. ft. footprint of this two-story custom home was used as the basis for the foundation cost comparisons in Table 1, and for calculating foundation + flood insurance costs in Table 3. The footprint includes the porches, but not the garage.
A raised wood floor system is a cost-competitive alternative to a concrete slab system, especially in areas where the builder must meet a minimum "lowest floor elevation" at or above the Base Flood Elevation (BFE) required by local floodplain management ordinances.

As shown in Table 1, the cost of building a raised floor compares favorably to the cost of a slab. Table 1 summarizes the cost of just the foundation for four common system types — two raised floor options and two slab options. The spread between the four options is only $1,735, with the cost of the elevated concrete slab option (at +1 BFE) the most expensive at $14,751, and the monolithic concrete slab-on-grade (at BFE) the least expensive at $13,016. The two raised wood floor options (at +2 BFE) priced in between at $14,074 for the pier-and-beam and $13,723 for the stem wall system.

In addition to cost-competitive construction for the builder as shown, a raised floor can mean significant savings for homeowners in flood-prone areas. Table 2 and Table 3 show how homeowners can realize dramatic reductions in annual flood insurance premiums with a raised floor system. Furthermore, the initial investment in a raised floor more than pays for itself over a 30-year mortgage. For this example, the net result for choosing a pier-and-beam raised wood floor at +2 BFE instead of a concrete slab-on-grade (slab-on-ground) at BFE is an overall savings of $6,605 for the homeowner as shown in Table 3. Savings begin immediately and grow larger during the life of the mortgage as shown in Figure 1.

Table 1 Cost-Comparisons: Raised Floor vs. Slab
RAISED FLOOR OPTION — PIER-AND-BEAM FOUNDATION + 2 BFE
 
Item
Amount
Material
Labor
Unit Cost
Cost
Excavation Footings
10.9 CY
23.45
23.45
$
255
Termiticide Soil Treatment
333 SF
0.24
0.21
0.45
$
150
Footings Concrete
14.4 CY
92.00
39.78
131.78
$
1,899
  #5 Rebar
296 LF
0.29
0.26
0.55
$
163
Foundation CMUs
500 Units
1.68
2.61
4.29
$
2,145
  #5 Rebar
222 LF
0.29
0.26
0.55
$
122
  Concrete
2.7 CY
92.00
39.78
131.78
$
354
Beams 6x6 PT
346 LF
3.08
0.60
3.68
$
1,273
Band Joists 2x12 PT
216 LF
1.70
0.55
2.25
$
486
Joists 2x12 PT
1910 LF
1.70
0.55
2.25
$
4,298
Anchor Straps 1-1/4x20 ga.
62 Each
0.89
0.89
$
55
Porch PT T&G Flooring
585 LF
0.41
0.20
0.61
$
359
Insulation R-19 Fiberglass
1920 SF
0.35
0.10
0.45
$
864
Subfloor 19/32 Sturd-I-Floor
1920 SF
0.57
0.29
0.86
$
1,651
Total Estimated Cost for Raised Floor Option — Pier-and-Beam
$
14,074
RAISED FLOOR OPTION — STEM WALL FOUNDATION + 2 BFE
 
Item
Amount
Material
Labor
Unit Cost
Cost
Excavation Footings
10.9 CY
23.45
23.45
$
255
Termiticide Soil Treatment
650 SF
0.24
0.21
0.45
$
293
Footings Concrete
7.3 CY
92.00
39.78
131.78
$
961
  #5 Rebar
442 LF
0.29
0.26
0.55
$
243
Foundation CMUs
734 Units
1.68
2.61
4.29
$
3,150
  #5 Rebar
311 LF
0.29
0.26
0.55
$
171
  Concrete
1.8 CY
92.00
39.78
131.78
$
242
Beams 6x6 PT
125 LF
3.08
0.60
3.68
$
460
Band Joists 2x12 PT
216 LF
1.70
0.55
2.25
$
486
Joists 2x12 PT
1910 LF
1.70
0.55
2.25
$
4,298
Still Plates 2x8 PT
221 LF
1.03
0.22
1.25
$
276
Anchor Bolts 1/2x6"
50 Each
0.28
0.28
$
14
Porch PT T&G Flooring
585 LF
0.41
0.20
0.61
$
359
Insulation R-19 Fiberglass
1920 SF
0.35
0.10
0.45
$
864
Subfloor 19/32 Sturd-I-Floor
1920 SF
0.57
0.29
0.86
$
1,651
Total Estimated Cost for Raised Floor Option — Stem Wall
$
13,723
 
SLAB OPTION — ELEVATED ON BACKFILLED PERIMETER WALL + 1 BFE
 
Item
Amount
Material
Labor
Unit Cost
Cost
Excavation Footings
10.9 CY
23.45
23.45
$
255
Termiticide Soil Treatment
2500 SF
0.24
0.21
0.45
$
1,125
Exterior Footings Concrete
7.3 CY
92.00
39.78
131.78
$
961
  #5 Rebar
442 LF
0.29
0.26
0.55
$
243
Foundation CMUs
734 Units
1.68
2.61
4.29
$
3,150
  #5 Rebar
311 LF
0.29
0.26
0.55
$
171
  Concrete
1.8 CY
92.00
39.78
131.78
$
242
Interior Footings Concrete
8.2 CY
92.00
39.78
131.78
$
1,076
  #5 Rebar
502 LF
0.29
0.26
0.55
$
276
Anchor Bolts 1/2x6"
50 Each
0.28
0.28
$
14
Fill Compacted Fill
156 CY
10.00
3.13
13.13
$
2,049
Slab Finish
2504 SF
0.42
0.42
$
1,052
 
Concrete
30.6 CY
92.00
43.20
135.20
$
4,137
Total Estimated Cost for Slab Option — Elevated
$
14,751
SLAB OPTION — MONOLITHIC ON GRADE at BFE
 
Item
Amount
Material
Labor
Unit Cost
Cost
Excavation Footers
10.9 CY
23.45
23.45
$
255
Termiticide Soil Treatment
2500 SF
0.24
0.21
0.45
$
1,125
Exterior Footings Concrete
22.9 CY
92.00
39.78
131.78
$
3,020
  #5 Rebar
442 LF
0.29
0.26
0.55
$
243
Interior Footings Concrete
8.2 CY
92.00
39.78
131.78
$
1,080
  #5 Rebar
502 LF
0.29
0.26
0.55
$
276
Anchor Bolts 1/2x6"
50 Each
0.28
0.28
$
14
Fill Compacted Fill
82 CY
10.00
3.13
13.13
$
1,075
Formwork 2x8 Exterior
221 LF
0.90
1.59
2.49
$
550
  2x4 Interior
95 LF
0.40
1.59
1.99
$
189
Slab Finish
2504 SF
0.42
0.42
$
1,052
  Concrete
30.6 CY
92.00
43.20
135.20
$
4,137
Total Estimated Cost for Slab Option — Monolithic on Grade
$
13,016

Source: Estimate prepared by Thomas Stevens, III, Florida Certified Building Contractor, St. Pete Beach, Florida, using MEANS cost data, January 2003. Based on a 2,744 sq. ft. foundation footprint for a two-story house required to meet the strict Florida Building Code.
BFE = base flood elevation     CY = cubic yards     SF = square feet     LF = lineal feet     CMUs = concrete masonry units     PT = pressure treated     T&G = tongue & groove